September 2, 2008
Concrete in stall barn aisle is complete. Stalls are underway. The electric main panel has been installed. The main water hydrant has been installed. We have laid down tubing for radiant heating in the feed, tack, and show tack rooms. All interior vmatch has been installed in the indoor. All siding on the stall barn has been installed along with the exterior stall doors. Each of the six exterior stalls will have their own paddock directly attached to the stall.
Click on an image to get a bigger picture (View All)
August 2, 2008
Roof on the stall barn is complete along with the ceiling. All lights, fans, and speakers have been installed in the arena. Kick-boards and V-match installation in the arena is well underway.
Click on an image to get a bigger picture (View All)
July 18, 2008
Posts are in for the stall barn. Still more fill has been brought in. Kickboards on the northend have started being installed.
Click on an image to get a bigger picture
July 14, 2008
The foundation for the stall barn is complete. The west side and south side siding is complete besides the trim. The siding on the north side is in the works. Installation of lights has started.
Click on an image to get a bigger picture
July 08, 2008
Footings for the stall barn went in. Windows on the west end were installed along with some siding.
Click on an image to get a bigger picture
July 07, 2008
Ceiling is in.
Click on an image to get a bigger picture
July 01, 2008
The metal roof is complete.
Click on an image to get a bigger picture
June 24, 2008
Everything is now ready for the metal roof to go up
Click on an image to get a bigger picture
June 12, 2008
Today the crane put the trusses up.
Click on an image to get a bigger picture (View All)
June 11, 2008
The trusses are complete. The site for the stall barn has been filled and is ready for the footings.
Click on an image to get a bigger picture
May 28, 2008
The trusses are tied together in to 36' wide sections on the ground.
Click on an image to get a bigger picture
May 21, 2008
Trusses were delivered today. The north side wall frame is nearly complete. Fill for the stall barn is being layed down.
Click on an image to get a bigger picture
May 19, 2008
Today most of the posts were installed.
Click on an image to get a bigger picture
May 15, 2008
The foundation for the arena is complete They have started adding the foundation drains and are back filling.
Click on an image to get a bigger picture
April 24, 2008
Forms came off the west side foundation while more concrete was pour on the south wall foundation and footings.
Click on an image to get a bigger picture
April 23, 2008
Forms for the west side foundation went up and concrete was poured.
Click on an image to get a bigger picture
April 21, 2008
Concrete was poured for the west side footings.
Click on an image to get a bigger picture
April 19, 2008
Forms for the west side footings went in today.
Click on an image to get a bigger picture
April 17, 2008
More fill and trenches for the west side footings.
Click on an image to get a bigger picture
April 16, 2008
More fill today.
Click on an image to get a bigger picture
April 15, 2008
Fill was brought in today. To level the site, the west end is cut down and the east end is being built up with fill.
Click on an image to get a bigger picture